class="post-template-default single single-post postid-137 single-format-standard">
  • Client: USACE
  • Completion: On-going
  • Location: Paktika
  • Prime Contractor: Maruf Sharif Construction Company

Services Provided

  • Design
  • Supply & Installation
  • Start-up & Commissioning

This project consists of design, supply and installation of a new wastewater treatment plant (partial min aerated lagoon).

This WWTP was designed to handle waste water flow of 896 persons, with considering the 167 m3/average daily flow. The effluent quality should achieve to 30 mg/l BOD and TSS.

This treatment plant consist of lift station, headwork, aeration lagoon, settling lagoon, sludge pump, chlorination tank and sludge drying bed.